Open
Demo state7
In progress
Demo state1
Done
Demo state0
Add a task
Creates a local record owned by the persona currently selected.
Open
7 task(s)
Book independent witness for smoke control re-test
TSK-002 · Mar Casa · due 15 Oct 2026
Required before the integrated systems test can be scheduled.
Owner: Commissioning Manager · raised by fixture
Prepare three-option comparison for stone package
TSK-003 · Park Five · due 10 Oct 2026
Economy, balanced and specified premium options with explicit arithmetic.
Owner: Design Manager · raised by fixture
Reconcile claimed vs supported quantities for PA-SAM-07
TSK-004 · ELEVE · due 5 Oct 2026
Five lines reviewed; three carry flags.
Owner: Commercial / Cost Manager · raised by fixture
Confirm chiller factory slot before order-by date
TSK-005 · DWTN · due 18 Oct 2026
Illustrative long-lead item on the critical path of the scenario programme.
Owner: Commercial / Cost Manager · raised by fixture
Run interface workshop with utilities relocation team
TSK-006 · AYA · due 22 Oct 2026
Agree revised access sequence.
Owner: Project Manager · raised by fixture
Close out HSE observations in east core
TSK-007 · Mar Casa · due 9 Oct 2026
Three open observations in the working area.
Owner: Site Engineer / HSE · raised by fixture
Complete O&M manual upload for ELEVE tower
TSK-008 · ELEVE · due 2 Nov 2026
Dossier completeness below target in the scenario store.
Owner: Asset & Handover Manager · raised by fixture
In progress
1 task(s)
Re-issue level 02 work pack against revision C04
TSK-001 · Mar Casa · due 7 Oct 2026
Withdraw superseded C03 from the active work pack and confirm re-issue in the CDE.