Opening readiness matrix

Scenario readiness by asset and gate

Readiness here is an illustrative score computed from demonstration milestone and commissioning records. No date on this page is a publicly committed opening date.

Scenario readiness by asset

Average of illustrative milestone completion and commissioning readiness. Colour: below 35% red, 35–70% tan, above 70% green.

Scenario

Milestone gates

Sorted by forecast finish. Search by milestone, discipline or owner.

MilestoneProjectDisciplineBaselineForecastVarianceStatusOwner
Tower services risers ready for final connectionsMS-MAR-01 · 96% completeMar CasaMEP20 Aug 20264 Sept 2026+15dslippingProgramme Director
Substructure completeMS-SAM-01 · 100% completeELEVEStructures12 Sept 202612 Sept 20260dcompleteProject Manager
MEP riser installation — east coreMS-MAR-02 · 72% completeMar CasaMEP18 Sept 202616 Oct 2026+28dat riskProject Manager
Enabling works completionMS-G-RIVAGE-1 · 28% completeRIVAGEArchitecture15 Oct 202619 Oct 2026+4don trackProject Manager
Residential finishes material approvalMS-SQ-01 · 55% completePark FiveArchitecture10 Oct 20267 Nov 2026+28dat riskDesign Manager
Facade first panel installedMS-G-MAR-CASA-3 · 74% completeMar CasaFacade12 Nov 20267 Nov 2026-5don trackDesign Manager
Pre-handover snagging startMS-G-AYA-7 · 47% completeAYAMEP24 Nov 202618 Nov 2026-6don trackDesign Manager
Compliance stone cladding mock-up sign-offMS-SQ-02 · 40% completePark FiveCompliance24 Oct 202621 Nov 2026+28dat riskCompliance Reviewer
Smoke control functional testMS-MAR-03 · 18% completeMar CasaMEP6 Nov 20264 Dec 2026+28dat riskCommissioning Manager
MEP first fix completeMS-G-REGALIA-4 · 12% completeRegaliaArchitecture14 Jan 202710 Jan 2027-4don trackCommissioning Manager