Payment application check
Claimed against evidence-supported
Every application, rate and quantity here is an illustrative demonstration record. Flags are findings against fictional demo delivery partners only, and nothing on this page can certify or pay anything.
Claimed in application
ScenarioAED 61.5m
Submitted 28 Sept 2026 by Demo delivery partner B.
Claimed by line arithmetic
ScenarioAED 29.8m
Rate × claimed quantity, summed.
Evidence-supported
ScenarioAED 28.7m
Rate × quantity supported by a field evidence reference.
Retention at 5%
ScenarioAED 1.4m
Net of retention AED 27.2m.
Line-by-line assessment
4 of 5 lines carry a flag. Evidence links open the inspection register.
| BOQ ref | Description | Rate | Claimed qty | Supported qty | Claimed | Supported | Difference | Evidence | Flag |
|---|---|---|---|---|---|---|---|---|---|
| 03.20.015 | Reinforcement to transfer slabs, grade B500BPL-SAM-07-01 · per tonne | AED 4,250 | 1,480 | 1,315 | AED 6.3m | AED 5.6m | AED 701,250 | INS-SAM-0442 | quantity gap |
| 03.30.040 | Structural concrete C40/50 to transfer zone CPL-SAM-07-02 · per m3 | AED 1,180 | 6,200 | 6,200 | AED 7.3m | AED 7.3m | — | INS-SAM-0442 | clean |
| 04.10.022 | Blockwork and plaster to zone C internal wallsPL-SAM-07-03 · per m2 | AED 310 | 18,400 | 18,400 | AED 5.7m | AED 5.7m | — | INS-SAM-0442, INS-SAM-0451 | duplicate evidence |
| 07.60.011 | Roof waterproofing membrane, two-layer systemPL-SAM-07-04 · per m2 | AED 265 | 9,100 | 7,400 | AED 2.4m | AED 2.0m | AED 450,500 | none | missing approval |
| 08.40.003 | Glazed curtain wall to north elevationPL-SAM-07-05 · per m2 | AED 3,950 | 2,050 | 2,050 | AED 8.1m | AED 8.1m | — | INS-SAM-0442 | rate mismatch |
Retention arithmetic
28,667,250 × 5% = 1,433,362.5 retained; net 27,233,887.5
Retention is applied on the evidence-supported amount at the stated contract percentage for this demonstration.
All demo applications
| Application | Project | Period | Claimed | Status | Party |
|---|---|---|---|---|---|
| PA-SAM-07 | ELEVE | September 2026 | AED 61.5m | under assessment | Demo delivery partner B |
| PA-MAR-14 | Mar Casa | September 2026 | AED 118m | under assessment | Demo delivery partner A |
| PA-SQ-11 | Park Five | September 2026 | AED 74.9m | certified | Demo fit-out specialist E |