Investment & cost forecast

Scenario cost position by project

Scenario control budgets are seeded from each published value and then varied for demonstration. They are not approved budgets, and the published award values themselves are never changed.

Scenario control budget (tracked projects)

Scenario

AED 6.64bn

Illustrative aggregate of the tracked scenario budgets only.

Scenario estimate at completion

Scenario

AED 6.78bn

Illustrative aggregate.

Scenario variance

Scenario

AED 136m

EAC minus scenario control budget.

Scenario budget against estimate at completion

Illustrative values in AED million.

Scenario

Project detail

Published award shown alongside the illustrative scenario position so the two are never confused.

ProjectPublished valueScenario control budgetScenario committedScenario certifiedScenario EACScenario variance
TriaNot published Public factnot publishedAED 510m ScenarioAED 318mAED 158mAED 550mAED 40.4m
ELEVENot published Public factnot publishedAED 720m ScenarioAED 448mAED 340mAED 759mAED 39.5m
AYANot published Public factnot publishedAED 680m ScenarioAED 424mAED 232mAED 716mAED 35.6m
RIVAGENot published Public factnot publishedAED 620m ScenarioAED 386mAED 285mAED 651mAED 30.9m
Mar CasaAED 1.10bn Public factproject valueAED 860m ScenarioAED 536mAED 424mAED 880mAED 19.8m
TaliaNot published Public factnot publishedAED 310m ScenarioAED 193mAED 79.5mAED 319mAED 8.7m
RegaliaNot published Public factnot publishedAED 260m ScenarioAED 162mAED 97.4mAED 267mAED 6.6m
JannatNot published Public factnot publishedAED 290m ScenarioAED 181mAED 118mAED 290mAED -405,408
Park FiveNot published Public factnot publishedAED 940m ScenarioAED 585mAED 260mAED 936mAED -3.6m
DWTNNot published Public factnot publishedAED 1.45bn ScenarioAED 903mAED 638mAED 1.41bnAED -41.0m