Future-state Deyaar prototype · Public facts + illustrative operations

CEO · Mar Casa · Demo role, not authorization

Variation register

Illustrative variation pipeline

All variations here are demonstration records. Originators are fictional demo delivery partners. No published award value is altered by anything on this page.

Unapproved variations

Scenario

19

Draft, submitted or under review.

Unapproved value

Scenario

AED 494m

Largest single item

Scenario

AED 86.4m

Park Five facade-facing stone option change.

Variations

Search by title, reason or originator; filter by status; sort any column.

Scenario
Captured in
Additional ground improvement in localised zoneVO-RIVAGE-100Unforeseen ground condition recorded in field.RIVAGEAED 1.1mrejected7d24 Jun 2026Demo delivery partner AAsite PMIS
Interface works with adjacent packageVO-REGALIA-102Interface coordination with neighbouring package.RegaliaAED 3.8mdraft15d24 Sept 2026Demo delivery partner CAsite PMIS
Smoke control rectification and re-testVO-MAR-022Rectification arising from NCR-MAR-087.Mar CasaAED 4.2msubmitted21d24 Sept 2026Demo MEP specialist DAsite PMIS
Client-requested lighting upgradeVO-TALIA-101Client scope change request.TaliaAED 4.7mapproved8d3 Sept 2026Demo delivery partner AAsite PMIS
Client-requested lighting upgradeVO-AYA-101Client scope change request.AYAAED 5.4msubmitted18d5 Jun 2026Demo delivery partner AAsite PMIS
Client-requested lighting upgradeVO-PARK-FIVE-101Client scope change request.Park FiveAED 5.6mapproved22d8 Aug 2026Demo MEP specialist DAsite PMIS
Interface works with adjacent packageVO-MAR-CASA-102Interface coordination with neighbouring package.Mar CasaAED 7.7munder review20d17 Jul 2026Demo MEP specialist DAsite PMIS
Interface works with adjacent packageVO-DWTN-102Interface coordination with neighbouring package.DWTNAED 7.9mrejected3d17 Sept 2026Demo fit-out specialist EAsite PMIS
Additional ground improvement in localised zoneVO-PARK-FIVE-100Unforeseen ground condition recorded in field.Park FiveAED 11.0munder review8d5 Jun 2026Demo delivery partner CAsite PMIS
Interface works with adjacent packageVO-RIVAGE-102Interface coordination with neighbouring package.RIVAGEAED 11.9mrejected6d16 Jun 2026Demo delivery partner CAsite PMIS

32 of 32 illustrative records match. Export includes all filtered records.