Future-state Deyaar prototype · Public facts + illustrative operations

CEO · Mar Casa · Demo role, not authorization

Abu Dhabi

RIVAGE

The published section below is public fact with a source. Everything in the delivery section is an illustrative demonstration record.

Published value

Public fact

Not published

No public project value tracked.

Announced

Public fact

Not published

Announcement date as published.

Named child assets

Public fact

0

Children of one parent project. None carries an independent published budget.

Illustrative records joined here

Scenario

30

Across schedule, documents, field, commercial, procurement and risk.

  • Official Deyaar property identity
  • Construction snapshot states Q4 2027; page is undated and not live status

Child assets

Named components of the parent award. Values are never split or invented for children.

Public fact
AssetTreatmentIndependent budget

Illustrative cashflow shape

Scenario planned versus recorded actual. Demonstration values only.

Scenario

Scenario control budget

Scenario

AED 620m

Scenario committed

Scenario

AED 386m

Scenario certified

Scenario

AED 285m

Scenario EAC

Scenario

AED 651m

Illustrative delivery position

Records are joined by ID across the Asite product set.

Scenario
RecordReferenceStatusCaptured inOpen
MilestoneMS-G-RIVAGE-1 · Enabling works completionon track · forecast 19 Oct 2026Asite PMISReadiness
MilestoneMS-G-RIVAGE-2 · Primary structure topping outslipping · forecast 22 Mar 2027Asite PMISReadiness
MilestoneMS-G-RIVAGE-3 · Facade first panel installedat risk · forecast 9 Sept 2027Asite PMISReadiness
MilestoneMS-G-RIVAGE-4 · MEP first fix completeslipping · forecast 22 Apr 2027Asite PMISReadiness
MilestoneMS-G-RIVAGE-5 · Vertical transportation energisationat risk · forecast 20 Nov 2027Asite PMISReadiness
MilestoneMS-G-RIVAGE-6 · Landscape hard works completeslipping · forecast 3 Jun 2027Asite PMISReadiness
DocumentDOC-RIVAGE-100 · General arrangement plan — level 01 rev A01under reviewAsite CDERegister
DocumentDOC-RIVAGE-101 · Structural frame details — grid F rev B02under reviewAsite CDERegister
DocumentDOC-RIVAGE-102 · MEP services coordination model extract rev C03approved with commentAsite CDERegister
DocumentDOC-RIVAGE-103 · Facade bracket and anchor details rev A04rejectedAsite CDERegister