Abu Dhabi
RIVAGE
The published section below is public fact with a source. Everything in the delivery section is an illustrative demonstration record.
Published value
Public factNot published
No public project value tracked.
Announced
Public factNot published
Announcement date as published.
Named child assets
Public fact0
Children of one parent project. None carries an independent published budget.
Illustrative records joined here
Scenario30
Across schedule, documents, field, commercial, procurement and risk.
Published scope and parties
- Official Deyaar property identity
- Construction snapshot states Q4 2027; page is undated and not live status
Child assets
Named components of the parent award. Values are never split or invented for children.
| Asset | Treatment | Independent budget |
|---|
Illustrative cashflow shape
Scenario planned versus recorded actual. Demonstration values only.
Scenario control budget
ScenarioAED 620m
Scenario committed
ScenarioAED 386m
Scenario certified
ScenarioAED 285m
Scenario EAC
ScenarioAED 651m
Illustrative delivery position
Records are joined by ID across the Asite product set.
| Record | Reference | Status | Captured in | Open |
|---|---|---|---|---|
| Milestone | MS-G-RIVAGE-1 · Enabling works completion | on track · forecast 19 Oct 2026 | Asite PMIS | Readiness |
| Milestone | MS-G-RIVAGE-2 · Primary structure topping out | slipping · forecast 22 Mar 2027 | Asite PMIS | Readiness |
| Milestone | MS-G-RIVAGE-3 · Facade first panel installed | at risk · forecast 9 Sept 2027 | Asite PMIS | Readiness |
| Milestone | MS-G-RIVAGE-4 · MEP first fix complete | slipping · forecast 22 Apr 2027 | Asite PMIS | Readiness |
| Milestone | MS-G-RIVAGE-5 · Vertical transportation energisation | at risk · forecast 20 Nov 2027 | Asite PMIS | Readiness |
| Milestone | MS-G-RIVAGE-6 · Landscape hard works complete | slipping · forecast 3 Jun 2027 | Asite PMIS | Readiness |
| Document | DOC-RIVAGE-100 · General arrangement plan — level 01 rev A01 | under review | Asite CDE | Register |
| Document | DOC-RIVAGE-101 · Structural frame details — grid F rev B02 | under review | Asite CDE | Register |
| Document | DOC-RIVAGE-102 · MEP services coordination model extract rev C03 | approved with comment | Asite CDE | Register |
| Document | DOC-RIVAGE-103 · Facade bracket and anchor details rev A04 | rejected | Asite CDE | Register |