Future-state Deyaar prototype · Public facts + illustrative operations

CEO · Mar Casa · Demo role, not authorization

Dependency graph

From a field record to a programme consequence

Each node is a record in the shared illustrative store, joined by ID. Open any node to see the register it lives in.

Story A — Mar Casa MEP commissioning readiness

Illustrative demonstration chain.

Scenario
  1. Field inspectionAsite FieldINS-MAR-1181

    MEP duct installation and damper witness

    fail on 19 Sept 2026 · 14 photos · Mar Casa residential level 02 — east core

  2. Non-conformanceAsite FieldNCR-MAR-087

    Smoke damper installed to superseded revision C03

    high severity · AED 4.2m illustrative cost · 21 days impact · Demo MEP specialist D

  3. Controlled drawingAsite CDEDOC-MAR-MEP-204

    Smoke control zoning layout — residential levels rev C04

    Supersedes revision C03, which was the revision witnessed on site.

  4. RFIAsite CDERFI-MAR-442

    Damper type confirmation at level 02 smoke zone boundary

    overdue · raised 8 Sept 2026 · due 22 Sept 2026

  5. Commissioning systemAsite PMISCX-MAR-CASA-1

    Smoke control

    1% ready · Open NCR-MAR-087 — dampers installed to superseded revision; re-test required before integrated test.

  6. MilestoneAsite PMISMS-MAR-03

    Smoke control functional test

    baseline 6 Nov 2026 → forecast 4 Dec 2026

  7. MilestoneAsite PMISMS-MAR-04

    Integrated fire and life-safety systems test

    baseline 10 Dec 2026 → forecast 14 Jan 2027

  8. Scenario readiness gateAsite PMISMS-MAR-05

    Scenario operational readiness gate

    baseline 22 Jan 2027 → forecast 25 Feb 2027 — illustrative, not a committed opening date

What this chain is for

The point of the chain is traceability: a consequence at programme level can be walked back to the field record that created it, and the evidence for each step is held in the product that captured it. In this prototype the records are illustrative, but the structure is the one the Asite product set already captures.