Published value
Public factNot published
No public project value tracked.
Announced
Public factNot published
Announcement date as published.
Named child assets
Public fact0
Children of one parent project. None carries an independent published budget.
Illustrative records joined here
Scenario35
Across schedule, documents, field, commercial, procurement and risk.
Published scope and parties
- Official property page identifies Jebel Ali location
- Construction snapshot states Q2 2027; page is undated and not live status
Child assets
Named components of the parent award. Values are never split or invented for children.
| Asset | Treatment | Independent budget |
|---|
Illustrative cashflow shape
Scenario planned versus recorded actual. Demonstration values only.
Scenario control budget
ScenarioAED 720m
Scenario committed
ScenarioAED 448m
Scenario certified
ScenarioAED 340m
Scenario EAC
ScenarioAED 759m
Illustrative delivery position
Records are joined by ID across the Asite product set.
| Record | Reference | Status | Captured in | Open |
|---|---|---|---|---|
| Milestone | MS-SAM-01 · Substructure complete | complete · forecast 12 Sept 2026 | Asite PMIS | Readiness |
| Milestone | MS-SAM-02 · Tower envelope watertight | at risk · forecast 19 Feb 2027 | Asite PMIS | Readiness |
| Milestone | MS-G-ELEVE-1 · Enabling works completion | at risk · forecast 23 Oct 2027 | Asite PMIS | Readiness |
| Milestone | MS-G-ELEVE-2 · Primary structure topping out | at risk · forecast 8 Jul 2027 | Asite PMIS | Readiness |
| Milestone | MS-G-ELEVE-3 · Facade first panel installed | slipping · forecast 5 Apr 2027 | Asite PMIS | Readiness |
| Milestone | MS-G-ELEVE-4 · MEP first fix complete | on track · forecast 20 Sept 2027 | Asite PMIS | Readiness |
| Document | DOC-SAM-STR-061 · ELEVE transfer slab reinforcement — zone C rev A05 | approved | Asite CDE | Register |
| Document | DOC-ELEVE-100 · General arrangement plan — level 01 rev A01 | approved with comment | Asite CDE | Register |
| Document | DOC-ELEVE-101 · Structural frame details — grid F rev B02 | approved | Asite CDE | Register |
| Document | DOC-ELEVE-102 · MEP services coordination model extract rev C03 | approved | Asite CDE | Register |