Dubai Silicon Oasis
Tria
The published section below is public fact with a source. Everything in the delivery section is an illustrative demonstration record.
Published value
Public factNot published
No public project value tracked.
Announced
Public factNot published
Announcement date as published.
Named child assets
Public fact0
Children of one parent project. None carries an independent published budget.
Illustrative records joined here
Scenario30
Across schedule, documents, field, commercial, procurement and risk.
Published scope and parties
- Official Deyaar property identity
- Past snapshot target September 2026 does not establish delay or completion
Child assets
Named components of the parent award. Values are never split or invented for children.
| Asset | Treatment | Independent budget |
|---|
Illustrative cashflow shape
Scenario planned versus recorded actual. Demonstration values only.
Scenario control budget
ScenarioAED 510m
Scenario committed
ScenarioAED 318m
Scenario certified
ScenarioAED 158m
Scenario EAC
ScenarioAED 550m
Illustrative delivery position
Records are joined by ID across the Asite product set.
| Record | Reference | Status | Captured in | Open |
|---|---|---|---|---|
| Milestone | MS-G-TRIA-1 · Enabling works completion | slipping · forecast 28 Feb 2027 | Asite PMIS | Readiness |
| Milestone | MS-G-TRIA-2 · Primary structure topping out | on track · forecast 16 Nov 2027 | Asite PMIS | Readiness |
| Milestone | MS-G-TRIA-3 · Facade first panel installed | at risk · forecast 31 May 2027 | Asite PMIS | Readiness |
| Milestone | MS-G-TRIA-4 · MEP first fix complete | on track · forecast 3 Jan 2028 | Asite PMIS | Readiness |
| Milestone | MS-G-TRIA-5 · Vertical transportation energisation | on track · forecast 23 Nov 2027 | Asite PMIS | Readiness |
| Milestone | MS-G-TRIA-6 · Landscape hard works complete | slipping · forecast 20 Dec 2027 | Asite PMIS | Readiness |
| Document | DOC-TRIA-100 · General arrangement plan — level 01 rev A01 | approved with comment | Asite CDE | Register |
| Document | DOC-TRIA-101 · Structural frame details — grid F rev B02 | approved | Asite CDE | Register |
| Document | DOC-TRIA-102 · MEP services coordination model extract rev C03 | approved | Asite CDE | Register |
| Document | DOC-TRIA-103 · Facade bracket and anchor details rev A04 | rejected | Asite CDE | Register |